Sidewalk

Project Details:
📅 Start Date: Monday, February 24th
Completion Time: Estimated 120 days
📍 Location: Starting at the NE corner of Carthage Square, working west, with the interior being completed last.

🚧 What to Expect:
Sidewalk replacements & enhancements for better pedestrian access
Walkways will remain wheelchair accessible
Traffic reduced to one lane in front of construction site.
Business access will remain open—no closures!
Some nighttime work to minimize daytime disruptions
Redesigned bump-outs with added greenery for smoother parade routes

💡 Why It Matters?
This project will enhance accessibility, improve the streetscape, and create a more vibrant downtown while preserving Carthage’s charm and traditions.

We appreciate your patience and excitement as we work to make our downtown even better!

Questions or concerns? Reach out to us at (417) 237-7003.